And so it (finally) begins!

  • Writer: David Plummer
    David Plummer
  • Jan 14, 2018
  • 1 min read

Digging and Footers

With all the permitting finally completed, mid-December 2017 saw the much-awaited groundbreaking of the Sundogs B&B! Our builder J.C. Smith and the sub-contractor managed to dig / compact the foundation area and pour most of the footers before the big freeze starting on Christmas Day.


Opening day - and fun and relaxing times - are only months away!


ree

Christmas Day, 2017. Looking east.


ree

Christmas Day, 2017. Panorama looking east.


ree

Christmas Day, 2017. Looking west.


Foundation wall

Basement wall forms were able to be set in place despite the historically cold weather. Pouring the concrete, however, would have to wait until temperatures warmed up a bit.

ree

December 29, 2017. Looking east-northeast.


ree

December 29, 2017. Looking northeast.


ree

December 29, 2017. Panorama looking east-northeast.



The walls were poured on January 10, 2018, and the forms removed the following day. On the 11th we also met with a rep from Potomac Edison to discuss where and how power will be brought onto the property.


ree

January 11, 2018. Panorama looking northeast.


ree

January 11, 2018. Panorama looking east.


ree

January 11, 2018. Looking east.


 
 
 